A construction firm wants to turn empty offices at 23 Railway Street, Chatham, into an 18-bedroom self check-in hotel with no parking. The plans went in on 19 November.

Empty offices above the shops at 23 Railway Street in Chatham could become an 18-bedroom hotel where guests check themselves in. The building has no car park, and none is planned.

The application, MC/26/2233, was received and validated by Medway Council on Thursday 19 November (Medway Council planning register). It was submitted by DHA Planning on behalf of Spencer Charles Construction Ltd, according to the planning statement filed with it.

Overview

The plans would:

  • convert the offices, which take up about two and a half floors of the 3.5-storey building, into 18 en suite bedrooms, each for two guests
  • add extra storeys to the lower part of the building, kept below the height of the main block and in the materials approved for an earlier scheme
  • keep guests’ entrance on Rome Terrace, with a bin store and four cycle spaces beside it
  • open a separate entrance to the basement for maintenance only
  • leave the ground-floor shop as it is

There would be no parking on site. Medway’s parking standards would normally expect one space per hotel bedroom, so 18 in this case, the statement says.

Why the developer says parking will cope

The applicant’s transport consultants counted spaces in five public car parks near the building on Thursday 5 November. Between them they hold 403 ordinary bays. According to the planning statement, they were:

Time Share of bays in use
8am 49.4%
Noon 98.5%
8pm 37.0%

The consultants argue that hotel guests mostly need parking overnight, when 254 spaces were free. They also say losing the office should ease daytime demand, which is when the car parks were nearly full.

Their trip forecast puts the hotel at 41 vehicle trips on a typical weekday, against 25 for the offices. That is 16 more a day. The building is about 260 metres from Chatham station and 150 metres from the nearest bus stop, the statement says.

Flats were approved here before

The building has been through the planning system three times since 2022, all for flats:

  • seven flats under permitted development rights, refused in December 2022
  • six flats with second and third floor extensions, approved in July 2023
  • seven flats with an extension, refused by the council in July 2024 but allowed on appeal in March 2025

The statement says the 2024 scheme was never built. The hotel’s extension copies its design.

The applicant says it discussed the hotel with council planners at a site meeting on 2 September. In its summary of the written advice that followed, officers raised no objection in principle and asked for a car park study plus details of deliveries, bins and cycle parking. The council’s own advice letter has not been published.

The statement also points to the council’s June 2025 retail and town centre study. It says more than a quarter of the floorspace surveyed in Chatham town centre was empty by 2024, twice the national average.

What it means for you

If you live or work near Railway Street or Rome Terrace, you can read the drawings and comment on the application page. On 21 November the register had not yet set a closing date for comments.

The building sits next to the Central Medway Air Quality Management Area. The applicant’s air quality assessment rates the risk of dust soiling nearby during building work as medium. According to the statement, council officers said at the pre-application stage that noise and air quality measures could be secured by planning conditions.

If you use the town centre car parks at lunchtime, the developer’s own survey found them close to full on a Thursday. Hotel guests would be looking for spaces mainly in the evening and overnight.