Medway Council wants to replace four ceilings, most basement and second-floor doors and a worn mosaic at the listed Brook Theatre. Decision due by 13 January.
Medway Council has asked for listed building consent to take out four ground-floor ceilings at the Brook Theatre in Chatham. Its architects say the old lath and plaster was already failing, and much of it had been opened up to investigate structural problems in the building.
The application, MC/26/2221, was validated on 18 November. It also covers replacing damaged doors that cannot meet modern fire and noise standards, and removing a worn strip of mosaic floor at the top of the main stairs (Medway Council planning register). The council’s target date for a decision is 13 January 2027.
Overview
The council, which owns the Grade II listed building, is asking to:
- remove the ceilings in the large dance studio, two smaller dance studios and the conference room, and fit new insulated plasterboard ceilings about 100mm lower, with the cornices copied to match
- replace all doors in the basement and on the second floor, plus a handful elsewhere that are beyond repair
- repair and keep most of the doors in the ground and first floor foyers
- replace the mosaic at the top of the internal stairs with stone to match the steps, where a new lift is going in
The ceilings in the main foyers, the corridor, the mayor’s parlour and the studio spaces are being kept and repaired.
Why the ceilings are coming out
The dance studios sit directly under the main auditorium and the studio theatre. According to the design, access and heritage statement by the council’s architects, Bailey Partnership, sound from rehearsals and shows upstairs made those rooms unusable while anything was happening above.
The council wants the studios to be let out throughout the day. Planning permission was already granted (MC/26/0967) for acoustic panels fixed to the old ceilings. The architects now say that would mean breaking out even more of the plaster to find the joists, then repairing it again. They call that “counter productive and non-economical”.
The statement says all the ground-floor ceilings needed repair because of earlier damage. It adds that “due to the structural failings in the building”, most of the ceilings and cornices have already been partly removed during opening-up work.
A lower ceiling also leaves a void for pipes and cables. Routing them from above is limited by the floors of the mayor’s parlour and the studio theatre. The conference room sits under a new AV hub behind the stage, which the architects expect to send noise downwards.
The doors
Stripping lead paint from most of the original doors exposed how badly some had fared. The statement lists missing panels and mouldings, large holes, cracks and drill holes left by years of temporary fixings.
Basement plant rooms need doors that resist fire for an hour, which the existing hollow and single-skin doors cannot do. The second-floor rooms will be the main dressing rooms, used mostly by young children, and every door there opens onto the escape route. The replacements are to copy the existing panelled style: four recessed panels in the basement and on the second floor, five on the ground and first floors.
What the building is
The Brook Theatre opened in 1900 as Chatham’s Municipal Buildings and town hall, and became a theatre and arts centre in 1985. A heritage impact assessment for the council rates it of “medium-high significance”, mainly for its architecture. The statement says no significant outside works are proposed.
When the council appointed Sinden as its contractor, it said work would take at least 18 months and the theatre was expected to reopen in 2027 (Medway Council). It listed the funding as:
- £6.5 million from the previous government’s Levelling Up Fund
- £300,000 from the Future High Streets Fund
- more than £10 million from the council
The new application does not give an updated reopening date.
What it means for you
The theatre stays closed while the restoration goes on. Anyone can comment on the application through the council’s planning register using reference MC/26/2221. The council’s culture team publishes updates on the works through Medway Tickets Live.